Project Overview: Ha’me Restaurant & Kitchen Renovation, Kwa’lilas Hotel
Type: Hotel Infrastructure Renovation
Client: Kwa’lilas Hotel
Location: 9040 Granville Street, Port Hardy, British Columbia
Completion Date: Completed
Budget: $150,000
Scope:
- Renovation of a 578 sq. ft. kitchen within the hotel.
- Upgraded electrical, mechanical, and plumbing systems.
- Selective demolition, structural modifications, and installation of new appliances and equipment.
- Interior finishes completed per design specifications.
Key Features:
- Enhanced hotel infrastructure.
- Fully commissioned, modernized kitchen facility.
Challenges & Solutions:
- Operating Kitchen: Conducted demolition and construction during graveyard shifts (11 PM–5 AM) to avoid disruptions.
- Structural Modifications: Collaborated with engineers to secure necessary approvals for modifications.
- Tight Deadlines: Expedited materials and subcontractor coordination to maintain project schedule.
- Plumbing Adjustments: Relocated grease interceptor to maintain proper grade while integrating with existing drainage lines.
Community Impact:
- Supports the hospitality and tourism sector by enhancing the hotel’s dining capabilities, improving guest experience, and promoting local economic growth.
Milestones:
- April 2024: Start demolition and removal works.
- May 2024: Complete structural framing and rough-in of mechanical, electrical, and plumbing (MEP) systems.
- June 2024: Finish concreting, ductwork, fire protection, and drywall installation.
- July 2024: Complete all MEP installations, painting, finishes, and appliance setup; install fire alarms and doors.
Project Duration: 50 days (April to July 2024)
Significance:
The Ha’me Kitchen renovation enhances the operational capacity and functionality of the Kwa’lilas Hotel, reinforcing its position as a premier destination for hospitality and tourism in Port Hardy.