Project Name and Location: 749 School Road Supportive Housing Project, Gibsons, British Columbia
Project Type: Supportive Housing Development
Project Scope: Construction of a three-story building comprising 40 self-contained studio units, each equipped with on-site support services to assist individuals experiencing or at risk of homelessness.
Completion Date: March 2021
Client or Partner Organizations:
- BC Housing: Funded and managed the construction, providing support services to residents.
- RainCity Housing: Operates the housing and delivers support services to residents.
- Town of Gibsons: Owns the land and facilitated the project’s development.
Budget and Scale: Not specified
Key Features or Highlights:
- 40 self-contained studio homes.
- On-site support services, including outreach workers, wellness checks, life skills training, employment assistance, and connections to community services.
- Priority given to Gibsons residents.
Challenges Faced and Solutions:
- Community Engagement: Conducted multiple community dialogues and public hearings to address concerns and incorporate feedback.
- Zoning and OCP Amendments: Successfully navigated amendments to the Official Community Plan and zoning bylaws to permit the development.
Community or Environmental Impact:
- Provides safe, secure housing for individuals experiencing or at risk of homelessness, enhancing community well-being.
- Reduces homelessness in the Gibsons area, contributing to social stability.
Key Services Provided:
- Permanent supportive housing with 24/7 on-site staff.
- Access to health, mental health, and addiction recovery services through Vancouver Coastal Health.
Project Timeline and Milestones:
- Spring 2018: Council applied under the Surplus Federal Real Property for Homelessness Initiative to acquire the property.
- March 2019: Federal government approved the land transfer.
- April 2019: Community dialogues held to share information and gather feedback.
- June 2019: Zoning and Official Community Plan amendment applications submitted.
- October 2019: Public hearing conducted; bylaws adopted in December 2019.
- January 2020: Demolition of the old RCMP building.
- August 2020: Construction of the new facility commenced.
- March 2021: Occupancy permit issued; residents began moving in.
Relevant Permits or Certifications:
- Zoning Amendment Bylaw No. 1065-49.
- Official Community Plan Amendment Bylaw No. 985-23.
For more information, please visit the Town of Gibsons’ official page on the 749 School Road Supportive Housing Project.